|
The NaTKiT1 Digital
I/O Kit provides the hardware needed for NaTKiT1 to accept user
input from micro switches. The kit consists of a 24 channel digital I/O
board, an external 50 way screw terminal board and a 50 way ribbon cable to
connect them. NaTKiT1 reserves 8 of the 24 channels for itself. In
the future the remaining 16 channels will be available to the user though the
current software issue does not support this.
INSTALLATION
First
the I/O board has to be installed in the PC. Remember to observe anti-static
precautions. Leave the mains lead from the PC plugged in to the wall
socket but turn the wall socket off. The PC's case should now be
at mains earth and touching the case will any static from you before handling
the I/O board.
a)
whip the cover off the PC,
b)
slide the I/O board into a vacant expansion slot,
c)
DON'T put the cover back on until you've tested everything so
as to ensure that it will work.
Now connect the terminal board to the I/O
board using the ribbon cable. The connectors on the ribbon have a key
way to ensure correct insertion. So you can test the installation
connect a single pole, normally open switch, between terminals 1 and 2 on the
terminal board. You could improvise a switch with two bits of wire.
To test the board you now have to tell
NaTKiT1 that the board is there. Run the programme select Engineer then
System maintenance. The choice Dig I/O Address (Hex)
should be showing Not there. Set the address to the I/O board's
default 2C0 and then select the TEST below Dig I/O Address
(Hex). Applying a short circuit between pins 1 and 2 should now make
the character T appear briefly. A short circuit between pins 3
and 4 should make RETURN appear briefly.
INPUTS
You are now ready to connect your
micro switches and go! Please note that if the switch is connected to 1
and 2 it can only initiate a test sequence. If the unit fails or, there
are operator decision tests or any other situation that requires input other
than T the operator will have to input from the keyboard or mouse.
If the switch is connected to 3 and 4, ie returning a carriage return,
then the default at each operator decision will be selected. This could
lead to confusing results.
OUTPUTS
The level between terminals 9 and
10 will be high when a test sequence or a calibration is executing, or the
Engineer facilities have been entered. The level is low at all other
times. A test sequence is "in progress" from when the operator
initiates the sequence and a pass or fail decision finally made.
If the Operator Fail Check is active and a unit fails then the
sequence is considered still in progress until either a pass is obtained or
the operator replies N to the "Retest this unit" prompt.
The level between terminals 11 and 12 will
be high when the FAIL prompt is visible and low at all other times.
If the Operator Fail Check is not active then this fail flag will
always be valid. If the Operator Fail Check is active then the
fail flag will only be valid when the Test in progress flag is low.
GROUND
All the even numbered terminals are
commoned and at ground.
|